Framing & Structure

    Deck Joist Span Calculator

    Looks up the maximum allowable span from the AWC DCA 6 prescriptive tables for the species, size and spacing you are using, accounts for cantilever, and tells you the smallest joist that will do the job.

    Inputs

    Measured between the ledger and the beam, or between beams.

    DCA 6 allows a cantilever of up to one quarter of the backspan.

    Recommended products for this project

    As an Amazon Associate we earn from qualifying purchases. Affiliate disclosure.

    Get the Smart Decking Calculator app

    Estimate decks on the go, save projects, and share with contractors.

    Download onApp StoreSOONGet it onGoogle Play

    Building something else? Try our sister calculators

    Frequently asked questions

    How far can a 2x8 deck joist span?
    In southern yellow pine, about 13 ft 1 at 12 inch spacing, 11 ft 10 at 16 inch, and 9 ft 11 at 24 inch. Douglas fir is slightly less and western red cedar less again. These are the DCA 6 prescriptive figures for a 40 psf live load, which is what residential deck codes assume.
    How far can a 2x10 span on a deck?
    Roughly 16 ft 2 at 12 inch spacing in southern yellow pine, 14 ft at 16 inch, and 11 ft 5 at 24 inch. The jump from 2x8 to 2x10 buys about two extra feet at typical spacing, which is often cheaper than adding a beam and the footings under it.
    What is a cantilever and how far can it go?
    The cantilever is the part of the joist that runs past the beam with nothing under it. DCA 6 allows up to one quarter of the backspan — so joists spanning 12 feet to the beam can cantilever 3 feet beyond it. Going further makes the deck bounce and can lift the inboard end.
    Does the species really matter?
    Yes, by two feet or more at the extremes. Southern yellow pine is the stiffest common treated species and western red cedar the least. Most pressure-treated stock in the eastern United States is southern yellow pine and most in the west is hem-fir or Douglas fir — check the grade stamp rather than guessing.
    Can I span further than the table allows?
    Only with an engineered design — steel, LVL, or a stamped calculation from a structural engineer. The prescriptive tables exist so that ordinary decks can be permitted without engineering. If your layout needs more span than they allow, that is the code telling you to add a beam or get a design.